PECO has announced as part of the company’s efforts to upgrade its local natural gas distribution system that nearly 9,000 feet of steel natural gas main will be installed on Lindenhurst Road causing lane closures as well as a full month closure.
The project, which is expected to take approximately five months, will begin in mid-May and is scheduled to be complete in October. Construction will begin at the Newtown Bypass (PA 332).
For the first several weeks of the project, work will occur from 7:00 p.m. to 5:00 a.m., Monday through Friday and will require lane closures. Work will then shift to occur between 9:00 a.m. and 3:00 p.m., Monday through Friday for the remainder of the project, requiring a detour.
For a four-week window, Lindenhurst Road will close completely. Additional details about the closure will be communicated in advance by PECO.